Description

Capital Development Authority (CDA) engaged Enviro Consult for providing Consultancy services for the infra-structural development of this Sector G-13 Islamabad. The scope of work included detailed engineering design of roads, storm water drainage system, water supply network, sanitary sewer system including trunk sewer, sewage treatment plant, bridges, culverts, retaining/embankment protection works, training of nullahs, overhead and underground water reservoirs etc. 

Area of the sector G-13 is about 700 acres and its layout plan has been prepared by CDA accommodating around 6000 residential plots of different categories with other amenities like markaz, sub-sector shopping areas, zone for government offices, parks, play fields, schools, mosques etc. The sector has been divided in four sub-sectors namely G-13/1, G-13/2, G-13/3 and G-13/4.

Project Additional Info

Client: Capital Development Authority Islamabad.

Location: Islamabad

Project Cost: 860 million

Project Completion: March 2014

Services Provided: 

  • Project Planning, 
  • Topographic Survey
  • Preliminary & Detailed Engineering Designs
  • Park and landscaping design
  • The design of about 13.0 Km of road network
  • Tender Document and Construction Drawings including bill of Quantities, Cost Estimation, Specifications and Conditions of contract etc.